Works By Others - P1
IMPORTANT NOTE FOR CLIENT
This document highlights and explains the necessary works to be completed to ensure the successful and problem free installation of your lift. Please don’t hesitate to ask if you have queries
(This is a generic scope of works and may vary for steel shafts)
(if you have any queries, please don’t hesitate to contact your project manager)
DURING CONSTRUCTION
- Provide dry, clean, safe and secure storage of the lift equipment whilst it is on site. The location of the storage area shall be agreed with Lift Shop and be close to the lift shaft and the machine room. Approximately 2 square meters please.
- Provide crane and or hoist the lift equipment if required.
- Supply and install and maintain shaft protection barricades to each lift entry.
SHAFT
- Shaft to be built to drawing dimensions
- Smooth, level pit floor is essential
- Shaft and pit must be able to sustain loads as specified and must comply with AS 1735
- Provide drain as per drawing with non-return valve
- Install conduits as per drawings A: 60mm dia for mains B: 32mm dia for door lock & landing wiring
- Ensure that the pit and shaft are dry, stripped, cleaned, and holes in shaft filled and free from all debris or other protrusions to enable Lift Shop to begin works on site
- Shaft wall to be plumb
- Lift shaft is to be smooth and rendered .The inside of the lift shaft is visible and so rendering and painting is highly recommended.
- Supply adequate fixing for door jambs on upper landing
- Complete surrounds and grout in door jambs, buttons, indications panels, floor sills and all penetrations and areas after the installation of the lift equipment.
- Lighting of lift area & landings to be 75 lux as per AS1735
MACHINERY SPACE
- Provide separate electrical supply to the machinery space. The lift requires its own circuit breaker in main board. Lift mains are to terminate to Lockable 3 Pole Isolator on Wall beside intended location of controller machinery. 20 amp single phase is usually required but job specific drawings should be checked and have priority. (in accordance with AS3000 please) The machinery space is 410 (d) x 410 (h) x 460 (w) , and needs to be approximately 3000mm from the lift. Conduit back to the unit is required.